Project Description

Complex construction process, made tangible through 3D visualization of phases

Copenhagen Airport is expanding the existing Terminal 2 airside with 4000 m² shopping and flow area. During construction the Airport must remain open to passengers and air traffic, requiring highly detailed planning ahead of actual execution on site.

To prepare for these complex circumstances Aarsleff wanted a visualization of the full sequence of phases for the general contractor bid. CN3 modelled the existing buildings, the planned buildings as well as the construction site on the basis of original drawings, available project material and many years of practical experience from construction sites.

From the model we produced a clear and credible 3D visualization of the construction phase plan.

REFERENCE DATA
CLIENT: Copenhagen Airports
ARCHITECT: Holm og Grut
CONTRACTOR: Aarsleff
PHASE: Tender

SERVICES
Visualization of phases